Telangana State Medical Services & Infrastructure Development Corporation (TSMSIDC)

S.No District Name Works Sanctioned Works Completed Works In Progress Works not Started
1 Karimnagar 25 0 0 0
TOTAL 25 0 0 0








S.No Project Id Project Name Agreement Date Completion Date as per Agreement Tech Sanction Amount Value of work done Scheme Stage of Work
1 213 Construction of Maternity Child Health (MCH) Center for excellency building at Karimnagar 05/02/2013 28/02/2014 200000000 140911000 NRHM
2 215 Contn of PHC building at Kaleshwaram 01/01/1970 01/01/1970 6850000 NRHM
3 762 Modification of Labor Room at CHC Huzurabad 19/04/2017 18/06/2017 3400000 2640978 NHM
4 763 Standardization of Birthing Unit at PHC Choppadandi (2nd Phase) 25/07/2018 25/10/2018 2250000 705000 NHM
5 764 Construction of New Labor Room at PHC Kothapally (v) 27/11/2017 26/01/2018 200000 265000 NHM
6 765 Establishment of HUB and Spoke Model Diagnostic Center at Karimnagar 26/04/2018 30/09/2018 3800000 3424000 NHM
7 766 Repairs and Renovation to UPHC at Mothazkhana in Karimnagar Municipality 21/11/2016 20/03/2017 750000 692269 NHM
8 767 Repairs and Renovation to UPHC Buttirajaram Colony in Karimnagar Municipality 19/09/2016 18/01/2017 900000 817220 NHM
9 781 Repairs and Renovation to the UPHC at Jaisettyramwell & Khilagadda 02/02/2017 27/05/2017 2550000 1019224 NHM
10 799 Repairs and Renovation to Standardization of Birthing Unit at CHC Gambhiraopet (2nd Phase) 20/08/2017 19/01/2018 2030000 1909000 NHM
11 802 Construction of Wellness Center at Mustafanagar (v) 01/01/1970 01/01/1970 700000 NHM
12 803 Construction of Wellness Cener at Damannapet (v) 01/01/1970 01/01/1970 700000 NHM
13 807 Repairs and Renovation to the UPHC P.S. Nagar Sircilla Municipality 19/09/2016 18/01/2017 800000 648273 NHM
14 808 Repairs and Renovation to the UPHC at Ambedkar Nagar in Sircilla Municipality 08/08/2017 07/10/2017 1400000 1153604 NHM
15 817 Repairs and Renovation to Standardization of Birthing Unit at CHC Manthani (2nd Phase) 01/01/1970 01/01/1970 6200000 NHM
16 818 Repairs and Renovtion to Standardization of Birthing Unit at PHC Kamanpur (3rd Phase) 30/08/2017 30/11/2017 450000 335441 NHM
17 834 Construction of 50 Bedded MCH Building at Manthani (V) 01/01/1970 01/01/1970 70000000 684000 NHM
18 836 Construction of 100 Bedded Mother Child Hospital at CHC Peddapally 26/09/2018 25/12/2019 170000000 128000 NHM
19 837 Repairs and Renovation to UPHC at Allur (v) Ramagundam Municipality 21/11/2017 20/02/2017 900000 755687 NHM
20 839 Repairs and Renovation to UPHC Janagoan (v) Ramagundam Municipality 19/10/2016 18/01/2017 975000 544973 NHM
21 841 Repairs and Renovation to UPHC at Laxmipur (v) Ramagundam Municiapality 19/10/2016 18/01/2017 1000000 925966 NHM
22 879 Repairs and Renovation to UPHC Addaguntapally and Ramagundam (package) 31/08/2016 30/11/2016 2950000 2345298 NHM
23 890 Construction of New Blood Bank Building at AH Godarikhani 16/01/2018 15/07/2018 3500000 1342000 NHM
24 891 Construction of New Blood Bank at CHC Peddapally 14/05/2018 13/08/2018 3500000 938000 NHM
25 892 Establishment of New Blood Bank at CHC Manthani 11/04/2018 10/07/2018 3500000 1899000 NHM